1.The pass-through shot blasting machine is a kind of shot blasting machine for us, but it is different from other cleaning machines, so it needs to be explained and understood, but in general, it is still a shot blasting machine equipment, and Different from shot blasting equipment, let's introduce its operation and maintenance below.
(1)Before starting work, check whether the formula of the cleaning solution is correct and whether the liquid level in the water tank meets the specified requirements.
(2) Set the heating temperature, heat the cleaning liquid, and pass the heater
(3) After the cleaning liquid is heated to the set temperature, the cleaning can be started. Press the button to start working, and then the water pump, conveying and cleaning will start to move.
(4) When the machine and equipment start to work, the operator can clean while conveying.
2. Maintenance
(1) Personnel should be designated to operate, use and maintain the machine, and be familiar with the machine's performance characteristics, master the operating procedures, and strictly implement them.
(2) During the operation of the machinery and equipment, once an abnormality is found, it should be shut down immediately and a technician will handle it.
(3) Lubrication should be carried out on a regular basis so that the bearings can work normally.
(4) Tap water and a certain amount of cleaning agent should be added regularly to supplement the consumption so that the liquid level can be maintained at a certain height.
(5) Regular maintenance is carried out to find problems in time.
(6) If the cleaning fluid cannot meet the cleaning requirements, it should be replaced.
For the through-type shot blasting machine, the corresponding operation precautions mainly include:
(1) The filter in the shot blasting machine should be cleaned once a week and checked. If there is any damage or breakage, it should be replaced in time without delay.
(2) Pay attention to the water level in the machine at any time, if the amount is insufficient, add it in time.
(3) The pressure in the equipment should be well controlled. Generally, the compressed air pressure is 0.4-0.6 MPa, and the cleaning fluid pressure is 0.6-0.8 Mpa.
(4) During the conveying operation, it is necessary to ensure that there are no workpieces at the exit, and it is also necessary to keep unblocked.